Details of 3rd party inspection Quality Assurance works completed / on hand
(Amount in Rs.)
Providing Project Management Consultancy for SHDP Phase-IV Works Under Kolar & Chikballapur District’s (Work Package Nos: 317, 318, 319, 320, 321, 322, 323, 324 & 325), Package No.: PMC/PH-4/BNG-IV
Estimated Cost (Lakhs) - 22412.38
Tendered cost - 22412.38
Actual date of completion- 06.10.2020
Construction of Bengaluru Dr.B.R.Ambedkar School of Economics (BASE) at Bengaluru University campus, Jnana Bharathi, Bengaluru urban District. (Buildings and Development works)-KHB
Estimated Cost (Lakhs) - 16699.51
Tendered cost - 16699.51
Actual date of completion- 21.09.2019
Project Monitoring and Quality Auditing Services for the work of Construction of Super Speciality Hospital in the premises of Gulbarga Institute of Medical Sciences at Kalaburagi -KHSDRP
Estimated Cost (Lakhs) - 12414.65
Tendere cost - 12414.65
Actual date of completion- 07.09.2019
Consultancy services for Project Management including, supervision, quality assurance, progress monitoring /reporting, measurement, billing and documentation
for the work of “Construction of 192 PC quarters at Audugodi (pkg-17), 128 PC quarters at K R Puram (pkg-18) and 64 PC + 128 SI quarters at Mysore road circle (pkg-19) under Police Gruha 2020 scheme”. pmc package – 07 - KSPH & IDCl-BNG
Estimated Cost (Lakhs) - 9268.52
Tendered cost - 9268.52
Actual date of completion- 30.07.2019
Consultancy services for Project Management including, supervision, quality assurance, progress monitoring /reporting, measurement, billing and documentation for the work of “Construction of 132 PC+ 12 SI quarters
in Mandya & Chamarajanagar District (pkg-06) and 156 PC quarters in Mysore district (pkg-07) under Police gruha 2020 scheme”. pmc package – 03-KSPH & IDCl-MYS
Estimated Cost (Lakhs) - 4614.72
Tendered cost - 4614.72
Actual date of completion- 09.07.2019
Project Management Consultancy for SHDP Phase-III works under BANGLORE circle, Package No.: BNG-I
Estimated Cost (Lakhs) - 19589.12
Tendered cost - 19589.12
Cost of Completion (Lakhs) - 19589.12
Actual date of completion- 27.03.2018
Project Management Consultancy for Construction of New Administrative Block Building in BEP premesis, Dr.Rajkumar Road, Rajajinagar, Bengaluru-KRDCL
Estimated Cost (Lakhs) - 2853.00
Tendered cost - 2853.00
Cost of Completion (Lakhs) - 3272.00
Actual date of completion- 23.03.2018
Project Management Consultancy services for the works in Bangalore Circle SHDP Phase-II
Estimated Cost (Lakhs) - 14065.53
Tendered cost - 14065.53
Cost of Completion (Lakhs) - 14065.53
Actual date of completion- March 2016
Project Management Consultancy services for the works in PWD, Bangalore Circle - SHDP Phase-I
Estimated Cost (Lakhs) - 6471.29
Tendered cost - 6471.29
Cost of Completion (Lakhs) - 6471.29
Actual date of completion- Nov 2014